We’ve been very busy the last few months with planning and designing our new facility here in Chillicothe, Ohio. Interior finish and construction of the initial 25,000 sq ft of our new 50,000 sq ft headquarters started a few weeks ago and it’s moving fast. Currently, walls are being framed and the electrical is being finished. The remaining 25,000 square feet will be empty for now. If everything goes according to plan, we’ll be operating the TYKMA Electrox North America operations out of our new facility by June. Take a look below at some of the progress!